Pubali Engineering & Construction Co. Ltd

+88 028418682




Coal Boiler Room for KSI at KEPZ of Karnaphuli Shoes Industries Ltd.

Employer: Karnaphuli Shoes Industries (KIS) Ltd. House # 14, Road # 7c, Uttara, Dhaka, Bangladesh.
Nature of Works:

 

Site Preparation.
Earth work Excavation: 432.00 cum.
Earth filling: 302.00 cum.
Lean Concrete: 86.00 cum.
RCC work: 637.00 cum.
Brick work (250mm): 63.00 cum.
Painting works: 508.00 sqm.
Plaster works: 508.00 sqm.
Floor Finishing works: 1,108.00 sqm.
Shuttering works: 1,098.28 sqm.
Re-bar works: 24.66 Tones.

Total Contract Price

BDT: 3.55 Crore

Start Date Completion Date
December: 2011
March: 2012
Completion
0%