PMP 2007-08/23/Overlay & DBST works (Tranche-3) under RHD, Dist.- Bogra.
Employer: Employers Representative, PMP 2007-2008 & Additional Chief Engineer, RHD, Planning & Maintenance Wing, Sarak Bhaban, Ramna, Dhaka.
Nature of Works:
Earth Shoulder: 2,307.6 m3 Hard Shoulder: 2,934.4m3 Premix Bituminous Carpeting: 920.15 m3 Tack Coat: 21,879.00 sqm. DBST Work: 1,73,491.800 sqm. DBS Wearing Course: 2,135.25 m3 Road Marking: 7,737.14 sqm.
Total Contract Price
BDT. 6.94 Crore
Start Date
Completion Date
June-2008
December-2010