+88 028418682

PMP/2005-2006/04, DBST & Overlay Works (i) Mymensingh-Raghurampur-Netrokona-Mohongonj-Sunamgonj (Ch: 6+800-21+800) (ii) Mymensingh-Raghurampur-Netrokona-Mohongonj-Sunamgonj Road (Ch: 21+800-40+950).

By:   sjnayem

PMP/2005-2006/04, DBST & Overlay Works (i) Mymensingh-Raghurampur-Netrokona-Mohongonj-Sunamgonj (Ch: 6+800-21+800) (ii) Mymensingh-Raghurampur-Netrokona-Mohongonj-Sunamgonj Road Employer:Employer’s Representative, PMP 2005-2006 & Additional Chief Engineer (RHD), Planning and Maintenance Wing, Sarak Bhaban, Ramna, Dhaka. Nature of Works:   Earth Work, Sub Base, Base Course, Asphalt Pavement & Road Marking. Total Contract Price BDT. 10.23 Crore Start Date Completion Date December-2004 […]

Toll Collection, Operation and Maintenance (T, O & M) works of the Hatikamrul-Bonpara New Road and associated works under Roads & Highways Department.

By:   sjnayem

Toll Collection, Operation and Maintenance (T, O & M) works of the Hatikamrul-Bonpara New Road and associated works under Roads & Highways Department. Employer: Executive Engineer, RHD, Road Division, Natore. Nature of Works:   Collection & Control of Toll revenue and banking of toll revenue. Safekeeping, handling, transporting & reconciliation Control of traffic through the […]

PMP 2007-08/19/Overlay works (Tranche-3) under RHD, Dist.- Rajbari.

By:   sjnayem

PMP 2007-08/19/Overlay works (Tranche-3) under RHD, Dist.- Rajbari. Employer: Employers Representative, PMP 2007-2008 & Additional Chief Engineer, RHD, Planning & Maintenance Wing, Sarak Bhaban, Ramna, Dhaka. Nature of Works:   DBS Wearing Course (Plant Method): 1,063.95m3 DBS Wearing Course (50mm thick- Avg.) : 9,473.889 m3 Bituminous Tack Coat: 1,98,044.251 sqm. Earth Shoulder: 10,301.25 m3 Road […]

185.99 M. long pre-stressed girder R.C.C. bridge in place of Pangashi Bailey Bridge at 9th K.M. of Sirajgonj-Raygonj Road under Road Division Sirajgonj during the year 2005-2006)

By:   sjnayem

185.99 M. long pre-stressed girder R.C.C. bridge in place of Pangashi Bailey Bridge at 9th K.M. of Sirajgonj-Raygonj Road under Road Division Sirajgonj during the year 2005-2006) Employer: Executive Engineer, RHD (C.C), Road Division, Sirajgonj. Nature of Works:   Earthwork, execution of In situ piles, Pile Load test, rebar, R.C.C casting, pre- stressing girder, staging, […]

PMP 2007-08/23/Overlay & DBST works (Tranche-3) under RHD, Dist.- Bogra.

By:   sjnayem

PMP 2007-08/23/Overlay & DBST works (Tranche-3) under RHD, Dist.- Bogra. Employer: Employers Representative, PMP 2007-2008 & Additional Chief Engineer, RHD, Planning & Maintenance Wing, Sarak Bhaban, Ramna, Dhaka. Nature of Works:   Earth Shoulder: 2,307.6 m3 Hard Shoulder: 2,934.4m3 Premix Bituminous Carpeting: 920.15 m3 Tack Coat: 21,879.00 sqm. DBST Work: 1,73,491.800 sqm. DBS Wearing Course: […]

Development/Preparation of Construction Yard for Padma Multipurpose Bridge project at Mawa (North), Munshigonj during the year 2010-2011.

By:   sjnayem

Development/Preparation of Construction Yard for Padma Multipurpose Bridge project at Mawa (North), Munshigonj during the year 2010-2011. Employer: Project Director, Bangladesh Bridge Authority, Padma Multipurpose Bridge, Shetu Bhaban, Banani, Dhaka. Nature of Works:   Excavation for GEO bags Slope Protection & Apron etc.: 1.60.000. 00 cum. Supply & Place of 250 kgs GEO bags for […]

Periodic Maintenance Program 2009-2010 (1st Tranche)

By:   sjnayem

Periodic Maintenance Program 2009-2010 (1st Tranche) Employer: Chief Engineer, RHD, Sarak Bhaban, Ramna, Dhaka. Nature of Works:   Earth Shoulder: 610.20 m3 Hard Shoulder: 2,025.0m3 Aggregate Base Type-I : 6961.95 m3 Bituminous Prime Coat: 45,079.95 sqm. Bituminous Tack Coat: 1,61,874.96 sqm. DBS Wearing Course: 10,056.74cum. Road Marking: 1,361.50 sqm. Saucer Drain : 2,600 L.meter Side […]

Factory Building and other ancillary work at Plot No. 133 to 148), DEPZ (Extension), Savar, Dhaka.

By:   sjnayem

Factory Building and other ancillary work at Plot No. 133 to 148), DEPZ (Extension), Savar, Dhaka. Employer: Kung Keng Textile (Bangladesh) Co. Ltd. DEPZ (Extension), Plot # 135-146, Savar, Dhaka, Bangladesh. Tel:+88-02-7701142-44, Fax:+88-02-7701145 E-mail: kktbabol-online.com Nature of Works:   (i) Factory Building Area (Dyeing and Spinning Factory Building- 21,675 Sqm.), Concrete work brick work, underground […]

Dyeing, Spinning Factory Building including 4 (four) storied Administrative Building & Dormitory House

By:   sjnayem

Dyeing, Spinning Factory Building including 4 (four) storied Administrative Building & Dormitory House Employer: Ring Shine Textile Ltd. Plot # 224-260, Extension Area DEPZ, Ganakbari, Savar, Dhaka, Bangladesh.Tel: +88-02-7701388 Nature of Works:   Dyeing Factory Building, Sweater Building, Spinning Building, Ware House, Canteen, Overhead Water Tank, and undergroundWater Reservoir, 4 Noose. Boundary Fence, RCC & […]

4-Storied Youngone Hi-Tech Sports Wear Annex Complex Building at DEPZ, Savar, Dhaka.

By:   sjnayem

4-Storied Youngone Hi-Tech Sports Wear Annex Complex Building at DEPZ, Savar, Dhaka. Employer: Youngone Hi-Tech Sports Ind. Ltd., DEPZ, Savar, Dhaka. Nature of Works:   Total Constructed Building Area: 4,500 sqm. Work permit, Health Safety & Environment, Earth work for foundation, rebar, scaffolding, steel form work, R.C.C casting, brick work, plastering, grouting, wood work, tiles, […]